After years of cancellations, reviews and ministerial point-scoring, the Cook Strait ferry programme finally has something freight operators can plan around. Detailed designs unveiled this week show two hybrid, rail-enabled vessels built by Guangzhou Shipyard International, due in 2029, with more room for trucks, rail wagons and passengers. On the water, this looks like a ferry designed for freight rather than for a press release. The open question has shifted to the land, where the cost of port works has roughly tripled and the government is already writing a fallback plan.
The ships are now the easy part
According to Ferry Holdings’ updated Statement of Intent, each vessel is about 200 metres long, carries around 1,500 passengers, offers 2.4km of vehicle lanes and takes up to 40 rail wagons, with a 30-year operating life. Rail freight loads straight on, cutting out handling steps that add cost and time on every crossing.
The ships carry solar panels, a battery storage system and the option to run on methanol later, and are expected to emit 30 percent less carbon per passenger and unit of cargo. Ferry Holdings chair Chris Mackenzie points to LIDAR bridge technology and redundancy in propulsion, steering and power, designed for the tight waters of the Marlborough Sounds and Wellington Harbour. Interislander’s operations chief Taru Sawhney says staff are “in full planning mode” for the transition.
Crucially, the shipbuilding contracts signed in November 2025 are fixed-price. That removes the shipyard blowout risk that helped sink iReX, the previous scheme whose costs ran toward $4 billion before it was cancelled. On the vessel side, the current programme deserves credit.
Where the money actually went
The ships themselves cost $596m. The wharves are another story. In May 2026, Treasury reviews put Wellington works at $167m and Picton at $110m. By July, BusinessDesk reported those had risen to $409m and $493m respectively, alongside $426m in programme management and contingency.
The programme hit the government’s $1.7b ceiling in June, forcing out some value-for-money, sustainability and safety enhancements. Port of Marlborough ($110m) and CentrePort ($100m) chipped in to keep the taxpayer share under the cap. Minister Winston Peters said the government had “only added cost where the taxpayer and ratepayer was not paying, where it added commercial value.” Those port contributions will be recovered through port charges on KiwiRail, which ultimately means freight customers.
Back-to-front, as critics warned
None of this should surprise anyone. In 2025, BusinessDesk’s Pattrick Smellie called it the back-to-front ferry deal: ships ordered from China before port designs and costings existed, with Tasmania’s stranded new ferries as the obvious warning. In May 2026, The Post reported that a Treasury-led review had found the land-side works carried “unacceptable levels of risk”, after the plan to reuse existing CentrePort assets collapsed when several proved too degraded to salvage.
The total now sits at $1.9 billion, and Mackenzie is openly preparing for slippage. “We will start alternative operational contingency planning with KiwiRail in 2027, to be activated should risks increase and erode available time contingency,” he said.
On schedule, for now
The good news is that the programme is moving. October’s Gate 3 Gateway review found it “progressing well” and within its funding envelope. Port works remain on schedule for 2029, with Wellington deconstruction due to finish in March 2027 and Picton’s new wharf construction starting in February 2027. CentrePort’s 2026 annual report describes a staging wharf on Southern Road and new piling already under way, and Treasury’s proactive release shows near-monthly oversight through 2026.
But the same Gateway review flags incomplete final designs and unresolved contracts for major works, and names relationship management between delivery parties as the single biggest risk, ahead of marine conditions. That is a governance problem, not an engineering one, and it is exactly where political churn does the most damage.
What freight businesses should plan for
The stakes are large. In 2025, Transporting New Zealand estimated about $30 billion of freight crosses Cook Strait each year. Its Billy Clemens warned then that with only four ferries operating, operators would have to manage capacity carefully “or we will see price hikes and costly delivery delays for businesses and consumers.” He also wanted “the party politics get parked” in favour of delivery.
That remains the right ask. Businesses moving goods between the islands should treat 2029 as a credible upgrade date while budgeting for tight capacity until then, and for a possible delay if the wharves slip. The ships are bought and paid for. Over the next two years, the test is whether Ferry Holdings, KiwiRail and two port companies can pour concrete as reliably as a Chinese shipyard welds steel, and whether whoever governs after 2026 has the discipline to leave them alone while they do it.
Sources
- RNZ: Designs for Kiwirail’s new Cook Strait ferries unveiled (2026-11-26)
- Ferry Holdings: Statement of Intent 2025-2029 (Updated August 2026) (2026-08)
- The Post: Back-up plan under way if ports not ready for ferries (2026-10-27)
- BusinessDesk: Port infrastructure underway as ink dries on Interislander deals (2026-07-19)
- RNZ: Ferry replacement project hit government’s $1.7b ceiling in June (2026-10-29)
- BusinessDesk: The back-to-front ferry deal (2025-11-19)
- The Post: Cook Strait ferry project hit with Treasury warning over delays and cost increase risk (2026-05-03)
- Ferry Holdings: Gateway Review Report – Gate 3 2026 (2026-10)
- CentrePort: Annual Report 2026 (2026)
- The Treasury: Ferry Holdings Limited Cook Strait Ferry Replacement Programme (2026-10-23)
- Transporting New Zealand: Timely delivery of port infrastructure essential for Cook Strait connection (2025-11-19)
Join the discussion
Add useful context, ask a good question, or challenge an idea — keep it specific and respectful.